Owner:
US Army Corp of
Engineers
Location: 1776 Niagara Street / Buffalo,
NY 14207
Contract amount:
$1.9
Million
→
Mobilization including access road way,
ramp and temporary office trailer.
→
Clearing and grubbing of access road
including removal of existing trees within
the
footprint of the ice control
structure/riprap.
→
Constructed stone access road to staging
area.
→ Removed
Phase I temporary water diversion
structure (South Half of Creek), and
installed Phase III temporary water
diversion structure (North Half of Creek).
→
Phase I rock excavation (South Half of
Creek).
→
Phase I drilling of rock anchors (South
Half of Creek).
→
Phase I concrete and reinforcing steel for
pier foundation (South Half of Creek).
→
Phase I Installation of steel encased
concrete piers (South Half of Creek).

→
Upstream and Downstream Sections of
concrete curb for revetment on North Bank
of
Creek.
→
Upstream and Downstream Sections of riprap
on North Bank of Creek.
→
Phase II rock excavation (North Half of
Creek).
→
Phase II drilling, installation, and
testing rock anchors (North Half of
Creek).
→
Phase II concrete and reinforcing steel
for 3’ thick pier foundation (North Half
of Creek).
→
Phase II installation of 5’ diameter steel
piers (North Half of Creek).
→
Phase II concrete and reinforcing steel
for 1’ thick pier foundation cap (North
Half of
Creek).
→
Phase II placement of reinforcing steel
and concrete for steel encased concrete
piers
(North Half of Creek).
→
Phase II installation, and testing rock
anchors (North Half of Creek).
→
Removal of Phase III temporary water
diversion structure (North Half of Creek).
→
Place Center Section of concrete curb for
revetment on North Bank of Creek.
→
Place Center Section riprap on North Bank
of Creek.
→
Complete New Entrance Road from Seneca
Street including guardrails and access
gate at entrance road.
→
Topsoil, seeding, and re-vegetation
planting.
→
Demobilization including cleanup and
removal of temporary fencing, temporary
utilities, and trailers.